In order to complete all of the studies prior to the preparation of the construction permit file, approximately 10 to 20 visits to the site (the equivalent of ½ day in total) by the team for performing surveys, environmental assessments and technical site visits for detailed design during the first 24 months.
Once the project is in operation, it is recommended to count at least 4 visits per year for the maintenance operations of the power plant.